Sep 25th 2026 Update
We are successfully done with D5 (19/19 column) Column erection of the Furnace building. To take you back from the start, we started with our first column B2 erection on 4th of Sep 2026. We are now on to filling the tie beams and floor beams.
Work continues according to schedule with an uncompromising focus on quality, precision engineering, and site safety. For more updates stick around with us.