Ongoing construction activities at Kinley Metals Private Limited include box beam welding for the Day Bunker, erection of PG beams and floor beams, and bar bending works at the 6700 mm level. Welding works for tie beams, floor beams, PG beams, and deck sheet channels are also actively progressing. In addition, fabrication of star beams at the 18,900 mm level is currently underway. All these activities are progressing simultaneously as part of the ongoing Furnace Building construction, with our workforce continuing to work towards achieving the project's construction milestones while maintaining quality and safety standards.

We sincerely appreciate the continued support and dedication of everyone involved. Stay connected with us for more updates on our construction progress and upcoming milestones.